July Update: Central Suites At Merchant House
The fit-out at Central Suites in Merchant House is almost complete with flooring and decoration underway. Combined with the additional car parking which has been provided on the estate, we hope that the fantastic facilities and bespoke fit-out will attract additional growing business to the Park and benefit the wider community. Our team have […]
June Update: Central Suites At Merchant House
We’ve been back at work on Central Suites at Merchant House following inevitable delays due to COVID-19. Project completion is anticipated to be mid-July which is fantastic under current restrictions. The Executive Lounge Area’s feature lighting is almost complete and the bar and kitchen area is ready to be installed! Please get in touch to […]